Nevada lien waivers
NVSTATUTORY FORM

Partial Unconditional Waiver and Release of Lien Rights

Nevada · Nevada Revised Statutes § 108.2457

When to Use This Form
When to sign
Sign after payment has cleared.
Who signs
Subcontractor, materialman, or laborer after payment confirmed
Free Nevada Template
Copy and fill in the blanks
PARTIAL UNCONDITIONAL WAIVER AND RELEASE OF LIEN RIGHTS
(Nevada Revised Statutes § 108.2457)

Claimant: _________________
Project: _________________
Owner: _________________
Through Date: _________________

Claimant has received payment of $_________ and waives and releases any lien rights or claims for labor, materials, or equipment furnished through the through date.

Signature: _________________
Title: _________________
Date: _________________

Fill in all blank fields before signing. In Nevada, using a non-statutory form may void the waiver. No notarization required.

⬇ Generate Filled PDF — First one free
Common Questions
90 days from the date you last furnished labor, materials, or equipment. Original contractors have 90 days from project completion or abandonment.
Legal disclaimer: The forms on this site are provided for general informational purposes only and do not constitute legal advice. Construction lien laws are complex and vary by project type and circumstances. Always consult a licensed construction attorney before relying on any lien waiver for a real project.