Unconditional Waiver and Release — Progress Payment
Arizona · Arizona Revised Statutes § 33-1008
When to Use This Form
When to sign
Sign after payment is confirmed received and cleared.
Who signs
Contractor, subcontractor, or materialman after payment clears
Free Arizona Template
Copy and fill in the blanks
UNCONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
(Arizona Revised Statutes § 33-1008)
Claimant: _________________
Customer: _________________
Owner: _________________
Property: _________________
Through Date: _________________
Claimant has received payment of $_________ and waives and releases any right to a mechanics lien or claim against a payment bond for the work through the through date.
Signature: _________________
Title: _________________
Date: _________________
Fill in all blank fields before signing. In Arizona, using a non-statutory form may void the waiver. No notarization required.
Legal disclaimer: The forms on this site are provided for general informational purposes only and do not constitute legal advice. Construction lien laws are complex and vary by project type and circumstances. Always consult a licensed construction attorney before relying on any lien waiver for a real project.